GRDA begins the largest upgrade project in its history when Unit 3 at Pensacola Dam is disassembled for major rehabilitation. Over the next six years, the remaining units will undergo the same procedure. When completed in April 2003, the combined generation capacity of Pensacola Dam is increased by approximately 20 percent, while Oklahoma’s oldest hydroelectric units are operating with many new turbine and generator components.