Floodwater Release Bulletin

At noon on Saturday, January 12:

• Grand Lake elevation was 744.98 feet. Daily target elevation for January 12 is 742 feet.

• At the direction of the United States Army Corps of Engineers, three (3) main gates were open at Pensacola Dam, discharging 23,451 cubic feet per second (cfs) of water.

• Five (5) units were online at the Pensacola Dam powerhouse, releasing 11,442 cfs of water through generation.

• Releases through floodgates and generation totaled 34,893 cfs.

• Inflows into Grand Lake totaled 34,177 cfs.

 

• Lake Hudson elevation was 621.34 feet. Normal elevation is 619 feet.

• At the direction of the United States Army Corps of Engineers, one (1) gate was open at Robert S. Kerr Dam, discharging 6,398 cubic feet per second (cfs) of water.

• Four (4) units were online at the Robert S. Kerr Dam powerhouse, releasing 32,940 cfs of water through generation.

• Releases through floodgates and generation totaled 39,338 cfs.

• Inflows into Lake Hudson totaled 46,880 cfs.